Small Home under 600 square Feet

Septic Update

I dropped the ball on the septic permitting.  Assumed the County and Septic Designer were on the same “path”, and yet I  was wrong.  The County was waiting for the designer to make changes to the original plan, and the designer thought the County would accept an “as-built”.  Thus I lost two weeks of productive time assuming this would resolve itself.  NOT.  My call forced the county to provide further instructions to the designer and  requesting all changes for the septic system be  in writing.  Wait time…another two weeks.